|
KEEPING
THE KRISTIN PROJECT UNDER CONTROL
Tom Henningsen
VP project management
Aker Kvaerner
When Tom Henningsen became responsible for planning
the engineering and construction of topsides on behalf of Aker
Kvaerner for its client Statoil, he turned to Safran. With millions
of dollars at stake, a project of this size and scope calls for
specialized computer software that is relied upon to provide the
kind of close project control demanded by a manager.
Henningsen had a key role in blending all the ingredients
for engineering procurement and construction into a seamless recipe
for success. He had to plan construction of the high pressure
and high temperature Kristin process deck at the Aker Stord yard
in Norway to ensure delivery of a completed platform facility
which would meet with an exacting client’s schedule. And he had
to do it all within a fixed time frame, coping with delays caused
by events over which he had no control.
Aker Kvaerner is a global engineering group providing
engineering and construction services, technology and solutions
in a range of sectors including oil and gas, refining, chemicals
and biotechnology. Employing 22,000 in more than 30 countries,
it has annual revenues in the region of US $4.5 billion. Aker
Kvaerner was one of the first customers for Safran’s project management
software back in 1996 and it was chosen as much because of its
geographical, cultural and historical ties with the oil and gas
industry.
So far, Safran’s software has been a contributing
factor in the success of many projects executed by Aker Kvarner
in recent years, including multibillion dollar projects such as
Snorre B, Grane, and Åsgard. Safran is now also being utilized
on Snøhvit and Ormen Lange.
Aker Kvaerner’s contribution to the Kristin project
is now successfully completed, both in terms of budget and time
schedule, and with no carry-over work. The platform set off from
Aker Kvaerner’s yard on the island Stord on 25 March 2005. The
unit arrived on the Halten Bank in the early hours of 29 March
with the assistance of five of the world’s largest seagoing tugs.
The installation work was completed by 15 May, and regular production
started in October 2005.
Risk. By 1996, major
oil and gas contractors found themselves bidding engineering procurement
and construction (EPC) projects on a lump sum basis. So it was
critical to carry out work the right way for the right price,
otherwise the client would expect the contractor to fund the cost
of any project over-run.
| “Developing a project management
system is part of the evolution of managing projects.” |
“If you look at handling responsibilities for just
engineering or procurement on a reimbursable basis, you are not
running a large amount of risk,” says Henningsen. “But if you
are running an EPC project on a lump sum you are running a large
risk with respect to the project’s interfaces.”
Consequently project managers had to find a way
to reduce that project risk, from late construction completion,
to delays in procuring key equipment, or manpower shortages -
all of which could jeopardize a project’s profitability for a
contractor operating on a fixed price bid. Managers needed a system
which could identify, catalogue and integrate all project elements
in a way which would optimize a build process, to ensure the best
possible project delivery in terms of both time and cost for the
client – and their own profitability.
“If you are just doing engineering for a project,
if you deliver engineering drawings, it does not matter if a fabrication
yard needs them a week earlier and could cost them another US
$1 million,” Henningsen illustrates. Also, if a fabricator received
compressor equipment after steel supports on a process deck were
completed, then it would be up to the fabricator to install the
compression equipment as best as he can - before the next deck
is built on top. It’s these kind of interfaces that Safran’s project
management software is designed to identify and manage in an optimal
way, to avoid clashes in a construction program.
Oil and gas industry.
“After 1996 when EPC-style projects became the name of the game,
it was to our competitive advantage to have the optimum support
with EPC contracts,” Henningsen says. “We needed a more sophisticated
planning system that was capable of networking with a multitude
of processes and a lot of activities in a very large activity
network.”
Several systems were evaluated by Aker Kvaerner
but it opted for Safran’s project management software because
the rival systems were considered to be less fl exible and less
powerful. Henningsen describes a rival system (Primavera) to be
more accountancy biased, a much more generalized system that could
be used by anybody, whereas Safran is designed to support the
complex projects in the oil and gas industry.


Although not involved in the selection of Safran,
Henningsen says: “Our evaluation at that time was that Safran
gave us the amount of business functionality that we wanted. Their
knowledge of the oil and gas industry and of the contracting business
and the challenges associated with it also played an important
part.”
| “Safran really excels when it
comes to handling complex projects in complex environments.” |
Approach. Henningsen
has extensive experience from the oil and gas industry from working
for Aker Kvaerner, and previously Kvaerner, since 1980. The transition
to Safran’s project management software in 1996 meant a more coherent
and systematic approach to the overall project management. For
example, previous systems could not match Safran’s sophisticated
functions for “What if?” scenarios to check the impact of events
further along a project’s cost and timing schedules.
As Henningsen explains: “Other systems that we were
looking at had bar charts and things which were quite good, but
they did not have the interfaces that we needed. Safran has the
functionality that we need and it is easy to sort information
in any shape or form. It is user friendly and you can extract
information both in a standard form and for reporting - you can
extract reports to analyze a particular aspect of a project.”
When he first started using Safran’s project management
software, Henningsen found that once he understood the operating
instructions, it was easy to begin working with Safran. “But you
do need experience to utilize its full capability. You don’t need
to be an engineer but you need to have been in the industry for
some time to understand the sequence of things.” On Kristin, Safran’s
project management software was relied upon to provide control
of all engineering, procurement and construction work. It controlled
the schedule by which engineering drawings had to be completed,
to interface with procurement and construction activities. Equipment
specifications, ordering and delivery checking were input to Aker
Kvaerner’s Kristin project execution model (PEM), which relied
on Safran.
Dozens and dozens of project management personnel
had direct access to the system during the Kristin programme.
Foremen, supervisors and engineers, had to extract information
from the PEM to see how their part in the work programme was progressing,
measured against specific project milestones. “There were a lot
of people communicating with Safran every day. On Kristin it was
in the region of 100 people.”
Specific. What makes
Safran so specific to oil and gas projects? “Developing a project
management system is part of the evolution of managing projects.
Safran allowed us to handle networks of previously unmanageable
sizes and levels of detail. Being able to add more details to
your schedule ensures accurate planning of the work to be completed
and all relevant and real-life interfaces between the different
activities allow us to exercise tighter control of our projects.
Previously we were constrained by the limitations of less sophisticated
software. Safran really excels when it comes to handling complex
projects in complex environments.”
One of the key points Henningsen makes about project
management is the need to retain control throughout the work,
from the initial engineering through procurement and construction
to delivery. “If you lose control of a project it can cost you
astronomical amounts of money. If you get delayed, you have to
pay damages to the client, and if you lose control you have to
recover and that recovery process is very costly. If you fall
behind the schedule you have to put a lot of manpower to work
in a non-productive sequence. It could easily cost you millions
of dollars.”
Safran’s project management software has gained
its prominence largely due to its fl exibility. “When you get
surprises, changes or variations, the system is very responsive
to putting these into chains of events. It is easily added in.
I think Safran is superior in that respect,” Henningsen says.
Two major elements of the Kristin platform’s construction
- a riser balcony and a fl are tower - were both completed late
by an outside contractor. Welding cracks on the fl are tower had
to be rectified before it could be installed on the platform.
This additional work had to be built into the project schedule.
Safran allowed Aker Kvaerner to manage it so that they did not
miss their delivery date for load out and mating with the Kristin
semi-submersible hull – built by Samsung in South Korea and delivered
in September 2004. “When we get incomplete work from other suppliers
or contractors, we are able to implement those [additional] activities
into our network and work it into a chain of events, allowing
us to reach our delivery target.”
The Kristin platform is now safely moored in the
North Sea, on schedule, and the first oil and gas arrived safely
in the platform’s production facility.

|